A large copper mine in Chile operates a fleet of 49 large haul trucks. The trucks employ diesel…

A large copper mine in Chile operates a fleet of 49 large haul trucks. The trucks employ

diesel-electric propulsion and have a rated capacity of 290 tonnes each.

Average fleet availability is 82%.

A breakdown of the causes of delay for the fleet is as follows:

Category Distribution of

downtime (%)

MTTR (hrs)

Motor 13.1% 8.34

Electrical 34.26% 4.79

Mechanical 28.54% 10.96

Structural 8.94% 6.56

Preventive

maintenance 6.95% 17.74

Accessories 3.41% 3.97

Miscellaneous 0.01% 0.92

Process delays 4.79% 7.94

Part A: Maintenance Performance Indices

Calculate:

(i) the total maintenance downtime (hrs) experienced by the fleet in one year (365

days). (1 mark)

(ii) total fleet up-time (hrs) in the same period (1 mark)

2

(iii) the average fleet utilisation assuming that “Process delays” incorporate

operational delays such as shift change etc. (1 mark)

(iv) the total operating hours (op hrs) of the fleet (1 mark)

(v) the expected Mean Time to Restore Service (MTTR) for the fleet (excluding

process delays). (1 mark)

(vi) the expected number of fleet maintenance interventions in one year (1 mark)

(vii) the expected number of delays/truck in each delay category (2 marks)

(viii) the Mean Time to Stoppage of the fleet (MTTS, in op hrs. This is distinct to

MTTF as not all interventions are unscheduled) (1 mark)

Attachments:

Save your time - order a paper!

Get your paper written from scratch within the tight deadline. Our service is a reliable solution to all your troubles. Place an order on any task and we will take care of it. You won’t have to worry about the quality and deadlines

Order Paper Now

 

"Looking for a Similar Assignment? Get Expert Help at an Amazing Discount!"